COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 30-Apr-2020

Freshwater Bayou Marsh Creation

PROJECT DATA

PROJECT: Freshwater Bayou Marsh Creation
PRIORITY LIST: 19 PROJECT NO: 1902 CWPPRA NO: ME-31 DNR NO: ME-31
PROJECT TYPE: Marsh Creation NET ACRES BENEFITTED: 279
REGION: 4 BASIN: Mermentau PARISH: Vermilion
LEAD AGENCY: NRCS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION: 1-Apr-2010 ( Actual )    
DESIGN COMPLETION: 1-Nov-2014 *    
CONSTRUCTION START: 1-Jul-2018 *    
CONSTRUCTION COMPLETION: 1-Aug-2019 *    
ESCROW AMENDMENT No:
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 1/20/2010 ( Actual )    
Phase 2 Approval: 22-Jan-2014 *    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 3 Charles W. Boustany
STATE SENATE DISTRICT: 999 Not Available
STATE HOUSE DISTRICT: 999 Not Available

Point of Contact:






,  
PHONES:  
Office:
Fax:

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 30-Apr-2020

Freshwater Bayou Marsh Creation

PROJECT LOCATION:

PROJECT DESCRIPTION:


PROJECT STATUS: (Project Status Last Updated: 19-Nov-2014 )

Milestones shown above are not correct. Federal Sponsor does not have access to change the information.

Scheduled Dates:
30% Review May 2016
95% Review August 2016
Contracting April 2017
Construction Start September 2017

FUND STATUS:

The current project estimate is $2,425,997 , which includes $2,425,997 for construction first costs, and $0 and $0 for 20 years of monitoring and operations and maintenance, respectively.