COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 6-Dec-2019

Kelso Bayou Marsh Creation TRANSFER

PROJECT DATA

PROJECT: Kelso Bayou Marsh Creation TRANSFER
PRIORITY LIST: 20 PROJECT NO: 2004 CWPPRA NO: CS-53 DNR NO: CS-53
PROJECT TYPE: Marsh Creation NET ACRES BENEFITTED: 274
REGION: 4 BASIN: Calcasieu/Sabine PARISH: Cameron
LEAD AGENCY: NRCS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION: 20-Sep-2011 ( Actual )    
DESIGN COMPLETION: 1-Apr-2013 *    
CONSTRUCTION START: 1-Sep-2014 *    
CONSTRUCTION COMPLETION: 1-Sep-2018 *    
ESCROW AMENDMENT No:
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 1/19/2011 ( Actual )    
Phase 2 Approval: 22-Jan-2014 *    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 3 Charles W. Boustany
STATE SENATE DISTRICT: 999 Not Available
STATE HOUSE DISTRICT: 999 Not Available

Point of Contact:






,  
PHONES:  
Office:
Fax:

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 6-Dec-2019

Kelso Bayou Marsh Creation TRANSFER

PROJECT LOCATION:

PROJECT DESCRIPTION:


PROJECT STATUS: (Project Status Last Updated: 19-Nov-2014 )

Milestones shown above are not correct. Federal Sponsor does not have access to change the information.

Scheduled Dates:
30% Review May 2016
95% Review August 2016
Contracting April 2017
Construction Start September 2017

FUND STATUS:

The current project estimate is $2,360,609 , which includes $2,360,609 for construction first costs, and $0 and $0 for 20 years of monitoring and operations and maintenance, respectively.