The Louisiana Coastal Wetlands Conservation and Restoration Task Force is initiating
procedures to deauthorize the Coastal Wetlands Planning, Protection, and Restoration
Act (CWPPRA) Terrebonne Bay Marsh Creation-Nourishment (TE-83) project as
requested by the Federal project sponsor, the U.S. Fish and Wildlife Service, and the
local project sponsor, the Louisiana Coastal Protection and Restoration Authority, due
to increased costs and uncertainty of project constructability associated with poor soil
conditions at the project site. Deauthorization of the TE-83 project would allow any
unused Phase 1 funds to be returned to the CWPPRA program for other use. This 20th
Priority Project List project is located in Region 3, within the Terrebonne Basin portion of
Terrebonne Parish.
The Task Force will consider the request to deauthorize the TE-83 project contingent
upon any written comments received. Written comments should be provided by
January 13, 2017 to the following address:
Colonel Michael N. Clancy
District Commander
U. S. Army Corps of Engineers, New Orleans District
Projects and Restoration Branch, CWPPRA Program Manager
7400 Leake Avenue
New Orleans, Louisiana 70118
If you need further information, please contact Mr. Mark Wingate, Deputy District
Engineer for Project Management, at (504) 862-2204 or Mr. Brad Inman, CWPPRA
Program Manager, at (504) 862-2124.
###