PROJECT STATUS REPORT as of 13-Sep-2024
PROJECT DATA
PROJECT: Lake Portage Land Bridge |
PRIORITY LIST: 8 | PROJECT NO: 0887 | CWPPRA NO: PTV-20 | DNR NO: TV-17 |
PROJECT TYPE: Hydrologic Restoration | NET ACRES BENEFITTED: 24 |
REGION: 3 | BASIN: Teche / Vermilion | PARISH: Vermilion |
LEAD AGENCY: NRCS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
CSA EXECUTION: | 07-Apr-2000 | ( Actual ) | ||
DESIGN COMPLETION: | 30-Aug-2002 | ( Actual ) | ||
CONSTRUCTION START: | 15-Feb-2003 | ( Actual ) | ||
CONSTRUCTION COMPLETION: | 15-May-2004 | ( Actual ) | ||
ESCROW AMENDMENT | 21-May-2002 | ( Actual ) | No: | 95 |
MONITORING PLAN APPROVAL: | 19-Jul-2004 | ( Actual ) | ||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 20-Jan-1999 | ( Actual ) | ||
Phase 2 Approval: | 20-Jan-1999 | ( Actual ) |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 3 | Charles W. Boustany |
STATE SENATE DISTRICT: | 22 | Fred H. Mills, Jr. |
STATE HOUSE DISTRICT: | 47 | Bob Hensgens |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
Quin Kinler Denham Springs, LA |
|
PROJECT STATUS REPORT as of 13-Sep-2024
Lake Portage Land Bridge
PROJECT LOCATION:
This project is located in Vermilion Parish within the Rainey Refuge.
PROJECT DESCRIPTION:
The objective of this project is to prevent the shoreline south of Lake Portage from breaching and creating another pass from Vermilion Bay to the Gulf. The project consists of backfilling a canal and armoring the beach with rock.
PROJECT STATUS: (Project Status Last Updated: 17-Apr-2012 )
Project construction was completed on May 15, 2004. Monitoring Plan was finalized on July 19, 2004
FUND STATUS:
The current project estimate is $1,181,129 , which includes $988,890 for construction first costs, and $87,096 and $105,143 for 20 years of monitoring and operations and maintenance, respectively.
LaCoast.gov | Project Managers' Technical Factsheet |