PROJECT STATUS REPORT as of 11-Oct-2024
PROJECT DATA
PROJECT: Cheniere au Tigre Sediment Trapping DEMO COMPLETE |
PRIORITY LIST: 6 | PROJECT NO: 0676 | CWPPRA NO: PTV-5 | DNR NO: TV-16 |
PROJECT TYPE: Sediment/Nutrient Trapping | NET ACRES BENEFITTED: 0 |
REGION: 3 | BASIN: Teche / Vermilion | PARISH: Vermilion |
LEAD AGENCY: NRCS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
CSA EXECUTION: | 20-Jul-1999 | ( Actual ) | ||
DESIGN COMPLETION: | 01-Feb-2001 | ( Actual ) | ||
CONSTRUCTION START: | 01-Sep-2001 | ( Actual ) | ||
CONSTRUCTION COMPLETION: | 02-Nov-2001 | ( Actual ) | ||
ESCROW AMENDMENT | 17-Mar-2000 | ( Actual ) | No: | 66 |
MONITORING PLAN APPROVAL: | ||||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 24-Apr-1997 | ( Actual ) | ||
Phase 2 Approval: | 24-Apr-1997 | ( Actual ) |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 3 | Charles W. Boustany |
STATE SENATE DISTRICT: | 25 | Dan "Blade" Morrish |
STATE HOUSE DISTRICT: | 47 | Bob Hensgens |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
Quin Kinler Denham Springs, LA |
|
PROJECT STATUS REPORT as of 11-Oct-2024
Cheniere au Tigre Sediment Trapping DEMO COMPLETE
PROJECT LOCATION:
PROJECT DESCRIPTION:
The objective of the project is to field test a conceptual device designed to trap sediment from the gulf tides, stabilize the on-going erosion on Cheniere au Tigre and build up portions of the coastline that have already eroded away. The success of the project will be gaged by the device perfoming to effectively reduce wave energies and significantly reduce or reverse erosion; have as few limitations as possible with regard to installation, cost, longevity, sediment trapping properties, site accessability, and risk failure and uncertainties; and effectively traps and retain sediment from the gulf coast wave action.
PROJECT STATUS: (Project Status Last Updated: 22-Mar-2002 )
A request for proposals was advertised in Feb 2000. No valid proposals received. Proceeding with design of a rock structure. Project advertised for bid. Bid came in over estimate. LDNR and NRCS shifted funds from monitoring to construction. Delay in getting new obligation due to internal COE procedures. Government order received July 13, 2001. Construction complete.
FUND STATUS:
The current project estimate is $596,781 , which includes $545,710 for construction first costs, and $39,410 and $11,660 for 20 years of monitoring and operations and maintenance, respectively.