PROJECT STATUS REPORT as of 11-Oct-2024
PROJECT DATA
PROJECT: Central Terrebonne Freshwater Enhancement TRANSFER |
PRIORITY LIST: 18 | PROJECT NO: 1802 | CWPPRA NO: 76 | DNR NO: TE-66 |
PROJECT TYPE: Hydrologic Restoration | NET ACRES BENEFITTED: 233 |
REGION: 3 | BASIN: Terrebonne | PARISH: Terrebonne |
LEAD AGENCY: NRCS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
CSA EXECUTION: | 04-May-2009 | ( Actual ) | ||
DESIGN COMPLETION: | 11/1/2016 12:00:00 AM | * | ||
CONSTRUCTION START: | 9/1/2017 12:00:00 AM | * | ||
CONSTRUCTION COMPLETION: | 7/1/2018 12:00:00 AM | * | ||
ESCROW AMENDMENT | No: | |||
MONITORING PLAN APPROVAL: | ||||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 21-Jan-2009 | ( Actual ) | ||
Phase 2 Approval: | 22-Jan-2017 | * |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 1 | Steve Scalise |
STATE SENATE DISTRICT: | 999 | Not Available |
STATE HOUSE DISTRICT: | 999 | Not Available |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
Quin Kinler Denham Springs, LA |
|
PROJECT STATUS REPORT as of 11-Oct-2024
Central Terrebonne Freshwater Enhancement TRANSFER
PROJECT LOCATION:
PROJECT DESCRIPTION:
PROJECT STATUS: (Project Status Last Updated: 08-Jun-2016 )
Project features are being incorporated into the Restore Act Project: Bayou Dularge Ridge, Marsh, and Hydrologic Restoration.
FUND STATUS:
The current project estimate is $1,345,158 , which includes $1,345,158 for construction first costs, and $0 and $0 for 20 years of monitoring and operations and maintenance, respectively.
LaCoast.gov | Project Managers' Technical Factsheet |