COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 29-Mar-2024

GIWW Bank Restoration of Critical Areas in Terrebonne

PROJECT DATA

PROJECT: GIWW Bank Restoration of Critical Areas in Terrebonne
PRIORITY LIST: 10 PROJECT NO: 1012 CWPPRA NO: TE-43 DNR NO: TE-43
PROJECT TYPE: Shoreline Protection NET ACRES BENEFITTED: 64
REGION: 3 BASIN: Terrebonne PARISH: Terrebonne
LEAD AGENCY: NRCS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION: 16-May-2001 ( Actual )    
DESIGN COMPLETION: 10/1/2004 12:00:00 AM *    
CONSTRUCTION START: 02-May-2013 ( Actual )    
CONSTRUCTION COMPLETION: 01-Feb-2014 ( Actual )    
ESCROW AMENDMENT 21-May-2002 ( Actual ) No: 100
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 10-Jan-2001 ( Actual )    
Phase 2 Approval: 20-Jan-2010 ( Actual )    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 6 William Cassidy
STATE SENATE DISTRICT: 21 R. L. "Bret" Allain II
STATE HOUSE DISTRICT: 51 Joe Harrison

Point of Contact:

DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE

Quin Kinler



Denham Springs, LA 
PHONES:  
Office:
Fax:

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 29-Mar-2024

GIWW Bank Restoration of Critical Areas in Terrebonne

PROJECT LOCATION:

This project is located along the GIWW in western Terrebonne Parish.

PROJECT DESCRIPTION:

This project will restore critical lengths of deteriorated channel banks, and stabilize/armor selected critical lengths of deteriorated channel banks with hard shoreline stabilization materials.

PROJECT STATUS: (Project Status Last Updated: 11-Jul-2012 )

CPRA assigned land rights to NRCS in April 2012. Project re-surveyed to verify design was still current. Project is scheduled for construction in December 2012.

FUND STATUS:

The current project estimate is $10,326,662 , which includes $9,332,533 for construction first costs, and $14,954 and $979,175 for 20 years of monitoring and operations and maintenance, respectively.