PROJECT STATUS REPORT as of 09-Sep-2024
PROJECT DATA
PROJECT: Thin Mat Floating Marsh Enhancement Demo COMPLETE |
PRIORITY LIST: 7 | PROJECT NO: 0782 | CWPPRA NO: CW-Demo | DNR NO: TE-36 |
PROJECT TYPE: Marsh Creation | NET ACRES BENEFITTED: 0 |
REGION: 3 | BASIN: Terrebonne | PARISH: Terrebonne |
LEAD AGENCY: NRCS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
CSA EXECUTION: | 16-Oct-1998 | ( Actual ) | ||
DESIGN COMPLETION: | 15-Dec-1998 | ( Actual ) | ||
CONSTRUCTION START: | 15-Jun-1999 | ( Actual ) | ||
CONSTRUCTION COMPLETION: | 10-May-2000 | ( Actual ) | ||
ESCROW AMENDMENT | 19-Mar-1999 | ( Actual ) | No: | 61 |
MONITORING PLAN APPROVAL: | ||||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 16-Jan-1998 | ( Actual ) | ||
Phase 2 Approval: |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 3 | Charles W. Boustany |
STATE SENATE DISTRICT: | 20 | Norby Chabert |
STATE HOUSE DISTRICT: | 53 | Lenar L. Whitney |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
Quin Kinler Denham Springs, LA |
|
PROJECT STATUS REPORT as of 09-Sep-2024
Thin Mat Floating Marsh Enhancement Demo COMPLETE
PROJECT LOCATION:
PROJECT DESCRIPTION:
This project will look at techniques to create and enhance thin floating mats of marsh, as well as the effects of water movement and sediments on these marshes. The objective is to induce development of thick, continually floating mats from a thin-mat flotant, and to determine the effects of water movement on the floats in areas with and without available sediments.
PROJECT STATUS: (Project Status Last Updated: 01-Jan-1990 )
Construction complete. Monitoring ongoing.
FUND STATUS:
The current project estimate is $538,101 , which includes $67,748 for construction first costs, and $470,353 and $0 for 20 years of monitoring and operations and maintenance, respectively.