COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 02-Jul-2026

Periodic Intro of Sediment &Nutrients Demo DEAUTHORIZED

PROJECT DATA

PROJECT: Periodic Intro of Sediment &Nutrients Demo DEAUTHORIZED
PRIORITY LIST: 9 PROJECT NO: 0903 CWPPRA NO: MF-DEMO DNR NO: MR-11
PROJECT TYPE: Sediment Diversion NET ACRES BENEFITTED:
REGION: 2 BASIN: Coastal Basins PARISH: Various Parishes
LEAD AGENCY: COE
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION:    
DESIGN COMPLETION:    
CONSTRUCTION START:    
CONSTRUCTION COMPLETION:    
ESCROW AMENDMENT No:
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE: 05-Nov-2008      
CASH FLOW PROECTS:        
Phase 1 Approval: 11-Jan-2000 ( Actual )    
Phase 2 Approval: 11-Jan-2000 ( Actual )    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 3 Charles W. Boustany
STATE SENATE DISTRICT: 1 A. G. Crowe
STATE HOUSE DISTRICT: 105 Christopher J. Leopold

Point of Contact:

DEPT. OF THE ARMY
CORPS OF ENGINEERS

Brad Inman
Project Manager
CEMVN-PM-OR
7400 Leake Avenue
New Orleans, LA 70160
PHONES:  
Office: (504) 862-1940
Fax: (504) 862-1892

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 02-Jul-2026

Periodic Intro of Sediment &Nutrients Demo DEAUTHORIZED

PROJECT LOCATION:

PROJECT DESCRIPTION:

The project concept involves the use of an existing Corps-leased hydraulic dredge to enrich the sediment content of an existing freshwater diversion.

PROJECT STATUS: (Project Status Last Updated: )

FUND STATUS:

The current project estimate is $88,009 , which includes $87,934 for construction first costs, and $75 and $0 for 20 years of monitoring and operations and maintenance, respectively.