COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 28-Mar-2024

Humble Canal Hydrologic Restoration

PROJECT DATA

PROJECT: Humble Canal Hydrologic Restoration
PRIORITY LIST: 8 PROJECT NO: 0885 CWPPRA NO: PME-15 DNR NO: ME-11
PROJECT TYPE: Hydrologic Restoration NET ACRES BENEFITTED: 378
REGION: 4 BASIN: Mermentau PARISH: Cameron
LEAD AGENCY: NRCS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION: 21-Mar-2000 ( Actual )    
DESIGN COMPLETION: 30-Jan-2002 ( Actual )    
CONSTRUCTION START: 01-Jul-2002 ( Actual )    
CONSTRUCTION COMPLETION: 01-Mar-2003 ( Actual )    
ESCROW AMENDMENT 17-May-2002 ( Actual ) No: 86
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL: 23-Feb-2004 ( Actual )    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 20-Jan-1999 ( Actual )    
Phase 2 Approval: 20-Jan-1999 ( Actual )    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 3 Charles W. Boustany
STATE SENATE DISTRICT: 25 Dan "Blade" Morrish
STATE HOUSE DISTRICT: 36 Chuck Kleckley

Point of Contact:

DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE

Quin Kinler



Denham Springs, LA 
PHONES:  
Office:
Fax:

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 28-Mar-2024

Humble Canal Hydrologic Restoration

PROJECT LOCATION:

This project is located on 5,500 acres of fresh and intermediate marsh in Cameron Parish, LA.

PROJECT DESCRIPTION:

It consists of replacing the existing Humble Canal structure to restore water management capabilities to the area.

PROJECT STATUS: (Project Status Last Updated: 12-Mar-2003 )

Construction complete March 2003.

FUND STATUS:

The current project estimate is $1,904,184 , which includes $660,247 for construction first costs, and $512,261 and $731,676 for 20 years of monitoring and operations and maintenance, respectively.

LaCoast.gov Project Managers' Technical Factsheet