PROJECT STATUS REPORT as of 04-Dec-2024
PROJECT DATA
PROJECT: East Cove Marsh Creation |
PRIORITY LIST: 31 | PROJECT NO: | CWPPRA NO: CS-88 | DNR NO: CS-88 |
PROJECT TYPE: Marsh Creation | NET ACRES BENEFITTED: 274 |
REGION: 4 | BASIN: Calcasieu/Sabine | PARISH: Cameron |
LEAD AGENCY: NRCS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
CSA EXECUTION: | ||||
DESIGN COMPLETION: | ||||
CONSTRUCTION START: | ||||
CONSTRUCTION COMPLETION: | ||||
ESCROW AMENDMENT | No: | |||
MONITORING PLAN APPROVAL: | ||||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 27-Jan-2022 | ( Actual ) | ||
Phase 2 Approval: |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | ||
STATE SENATE DISTRICT: | ||
STATE HOUSE DISTRICT: |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
Quin Kinler Denham Springs, LA |
|
PROJECT STATUS REPORT as of 04-Dec-2024
East Cove Marsh Creation
PROJECT LOCATION:
PROJECT DESCRIPTION:
PROJECT STATUS: (Project Status Last Updated: )
FUND STATUS:
The current project estimate is $2,765,587 , which includes $2,765,587 for construction first costs, and $0 and $0 for 20 years of monitoring and operations and maintenance, respectively.
LaCoast.gov | Project Managers' Technical Factsheet |