PROJECT STATUS REPORT as of 05-Dec-2025
PROJECT DATA
| PROJECT: Sabine Marsh Creation Cycles 6 & 7 |
| PRIORITY LIST: 27 | PROJECT NO: | CWPPRA NO: CS-81 | DNR NO: CS-81 |
| PROJECT TYPE: Marsh Creation | NET ACRES BENEFITTED: 900 |
| REGION: 4 | BASIN: Calcasieu/Sabine | PARISH: Cameron |
| LEAD AGENCY: FWS |
| LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
| CSA EXECUTION: | ||||
| DESIGN COMPLETION: | ||||
| CONSTRUCTION START: | ||||
| CONSTRUCTION COMPLETION: | 6/1/2026 12:00:00 AM | |||
| ESCROW AMENDMENT | No: | |||
| MONITORING PLAN APPROVAL: | ||||
| O and M PLAN APPROVAL: | ||||
| DEAUTHORIZATION DATE: | ||||
| CASH FLOW PROECTS: | ||||
| Phase 1 Approval: | 09-Feb-2018 | ( Actual ) | ||
| Phase 2 Approval: |
LEGISLATIVE DISTRICTS:
| CONGRESSIONAL DISTRICT: | ||
| STATE SENATE DISTRICT: | ||
| STATE HOUSE DISTRICT: |
Point of Contact:
DEPT. OF THE INTERIOR
FISH & WILDLIFE SERVICE
|
Darryl Clark Senior Field Biologist 200 Dulles Dr. Lafayette, LA 70506 |
|
PROJECT STATUS REPORT as of 05-Dec-2025
Sabine Marsh Creation Cycles 6 & 7
PROJECT LOCATION:
PROJECT DESCRIPTION:
PROJECT STATUS: (Project Status Last Updated: 12-Mar-2021 )
Currently CPRA is collecting survey and geotechnical data for engineering and design of this project.
FUND STATUS:
The current project estimate is $3,824,731 , which includes $3,824,731 for construction first costs, and $0 and $0 for 20 years of monitoring and operations and maintenance, respectively.