COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 19-Apr-2024

Kelso Bayou Marsh Creation TRANSFER

PROJECT DATA

PROJECT: Kelso Bayou Marsh Creation TRANSFER
PRIORITY LIST: 20 PROJECT NO: 2004 CWPPRA NO: CS-53 DNR NO: CS-53
PROJECT TYPE: Marsh Creation NET ACRES BENEFITTED: 274
REGION: 4 BASIN: Calcasieu/Sabine PARISH: Cameron
LEAD AGENCY: NRCS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION: 20-Sep-2011 ( Actual )    
DESIGN COMPLETION: 4/1/2013 12:00:00 AM *    
CONSTRUCTION START: 9/1/2014 12:00:00 AM *    
CONSTRUCTION COMPLETION: 9/1/2018 12:00:00 AM *    
ESCROW AMENDMENT No:
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 19-Jan-2011 ( Actual )    
Phase 2 Approval: 22-Jan-2014 *    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 3 Charles W. Boustany
STATE SENATE DISTRICT: 999 Not Available
STATE HOUSE DISTRICT: 999 Not Available

Point of Contact:

DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE

Quin Kinler



Denham Springs, LA 
PHONES:  
Office:
Fax:

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 19-Apr-2024

Kelso Bayou Marsh Creation TRANSFER

PROJECT LOCATION:

PROJECT DESCRIPTION:


PROJECT STATUS: (Project Status Last Updated: 19-Nov-2014 )

Milestones shown above are not correct. Federal Sponsor does not have access to change the information. Scheduled Dates: 30% Review May 2016 95% Review August 2016 Contracting April 2017 Construction Start September 2017

FUND STATUS:

The current project estimate is $1,265,369 , which includes $1,265,369 for construction first costs, and $0 and $0 for 20 years of monitoring and operations and maintenance, respectively.

LaCoast.gov Project Managers' Technical Factsheet