COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 19-Apr-2024

Perry Ridge West Bank Stabilization

PROJECT DATA

PROJECT: Perry Ridge West Bank Stabilization
PRIORITY LIST: 9 PROJECT NO: 0918 CWPPRA NO: PCS-26ii DNR NO: CS-30
PROJECT TYPE: Shoreline Protection NET ACRES BENEFITTED: 83
REGION: 4 BASIN: Calcasieu/Sabine PARISH: Cameron
LEAD AGENCY: NRCS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION: 25-Jul-2000 ( Actual )    
DESIGN COMPLETION: 01-Dec-2000 ( Actual )    
CONSTRUCTION START: 01-Nov-2001 ( Actual )    
CONSTRUCTION COMPLETION: 31-Jul-2002 ( Actual )    
ESCROW AMENDMENT 02-Mar-2001 ( Actual ) No: 80
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL: 19-Dec-2002 ( Actual )    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 11-Jan-2000 ( Actual )    
Phase 2 Approval: 10-Jan-2001 ( Actual )    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 3 Charles W. Boustany
STATE SENATE DISTRICT: 30 John R. Smith
STATE HOUSE DISTRICT: 33 Michael E. Danahay

Point of Contact:

DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE

Quin Kinler



Denham Springs, LA 
PHONES:  
Office:
Fax:

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 19-Apr-2024

Perry Ridge West Bank Stabilization

PROJECT LOCATION:

This project is located along the northern bank of the GIWW between Perry Ridge and the Sabine River in Calcasieu Parish.

PROJECT DESCRIPTION:

The project consists of installing rock along the bank to prevent further erosion.

PROJECT STATUS: (Project Status Last Updated: 06-Dec-2002 )

The Perry Ridge project approved on Priority List 4 was the first phase of this project. This is the second and final phase of the project. Task Force approved Phase 2 construction funding January 10, 2001. The rock bank protection is installed. The contract for the terraces and vegetation has been completed.

FUND STATUS:

The current project estimate is $2,204,688 , which includes $1,580,302 for construction first costs, and $94,146 and $530,240 for 20 years of monitoring and operations and maintenance, respectively.

LaCoast.gov Project Managers' Technical Factsheet