COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 04-Oct-2024

Bertrandville Siphon DEAUTHORIZED

PROJECT DATA

PROJECT: Bertrandville Siphon DEAUTHORIZED
PRIORITY LIST: 18 PROJECT NO: 1804 CWPPRA NO: BS-18 DNR NO: BS-18
PROJECT TYPE: Freshwater Diversion NET ACRES BENEFITTED:
REGION: 2 BASIN: Breton Sound PARISH: Plaquemines
LEAD AGENCY: EPA
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION: 15-Jun-2011 ( Actual )    
DESIGN COMPLETION: 4/8/2014 12:00:00 AM *    
CONSTRUCTION START:    
CONSTRUCTION COMPLETION:    
ESCROW AMENDMENT No:
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE: 16-Jan-2014      
CASH FLOW PROECTS:        
Phase 1 Approval: 21-Jan-2009 ( Actual )    
Phase 2 Approval: 21-Jan-2015 *    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 1 Steve Scalise
STATE SENATE DISTRICT: 999 Not Available
STATE HOUSE DISTRICT: 999 Not Available

Point of Contact:

ENVIRONMENTAL PROTECTION AGENCY
REGION 6

Paul Kaspar

EPA Region 6 (6WQ-EC)
1445 Ross Ave
Dallas, TX 75202
PHONES:  
Office: (214) 665-7459
Fax: (214) 665-6689

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 04-Oct-2024

Bertrandville Siphon DEAUTHORIZED

PROJECT LOCATION:

PROJECT DESCRIPTION:


PROJECT STATUS: (Project Status Last Updated: 21-Jan-2013 )

Project delays due to considerations of State Master Plan consistency and pursuit of landowner support.

FUND STATUS:

The current project estimate is $521,984 , which includes $521,607 for construction first costs, and $377 and $0 for 20 years of monitoring and operations and maintenance, respectively.