COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 23-Apr-2024

White Ditch Resurrection and Outfall Management DEAUTHORIZED

PROJECT DATA

PROJECT: White Ditch Resurrection and Outfall Management DEAUTHORIZED
PRIORITY LIST: 14 PROJECT NO: 1402 CWPPRA NO: BS-12 DNR NO: BS-12
PROJECT TYPE: Freshwater Diversion NET ACRES BENEFITTED:
REGION: 2 BASIN: Breton Sound PARISH: Plaquemines
LEAD AGENCY: NRCS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION: 11-Aug-2005 ( Actual )    
DESIGN COMPLETION: 11/1/2012 12:00:00 AM *    
CONSTRUCTION START:    
CONSTRUCTION COMPLETION:    
ESCROW AMENDMENT 09-Jun-2008 ( Actual ) No: 119
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE: 05-Jun-2013      
CASH FLOW PROECTS:        
Phase 1 Approval: 17-Feb-2005 ( Actual )    
Phase 2 Approval:    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 1 Steve Scalise
STATE SENATE DISTRICT: 1 A. G. Crowe
STATE HOUSE DISTRICT: 105 Christopher J. Leopold

Point of Contact:

DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE

Quin Kinler



Denham Springs, LA 
PHONES:  
Office:
Fax:

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 23-Apr-2024

White Ditch Resurrection and Outfall Management DEAUTHORIZED

PROJECT LOCATION:

The project is located in Plaquemines Parish, River aux Chenes Mapping Unit, White Ditch.

PROJECT DESCRIPTION:

The goal of the project is to reduce the erosion rate by introduction of freshwater, nutrients, and to lesser degree sediment into interior marshes. The proposed solution is (1) gated plug in the outfall channel (approximately 2 miles below siphon) to force water to enter interior marshes and (2) install additional siphon of same size (existing - two 50-inch diameter steel pipes currently allow approximately 250 cfs).

PROJECT STATUS: (Project Status Last Updated: 11-Jul-2012 )

Project team has agreed to move to deauthorization due to issues regarding location & operation of siphon.

FUND STATUS:

The current project estimate is $1,020,420 , which includes $1,020,420 for construction first costs, and $0 and $0 for 20 years of monitoring and operations and maintenance, respectively.