COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 25-Apr-2024

Chenier Ronquille Barrier Island Restoration DEAUTHORIZED

PROJECT DATA

PROJECT: Chenier Ronquille Barrier Island Restoration DEAUTHORIZED
PRIORITY LIST: 19 PROJECT NO: 1901 CWPPRA NO: BA-76 DNR NO: BA-76
PROJECT TYPE: Barrier Island NET ACRES BENEFITTED:
REGION: 2 BASIN: Barataria PARISH: Plaquemines
LEAD AGENCY: NMFS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION: 18-Aug-2010 ( Actual )    
DESIGN COMPLETION:    
CONSTRUCTION START:    
CONSTRUCTION COMPLETION:    
ESCROW AMENDMENT No:
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE: 22-Jan-2015      
CASH FLOW PROECTS:        
Phase 1 Approval: 20-Jan-2010 ( Actual )    
Phase 2 Approval: 23-Jan-2017 *    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 1 Steve Scalise
STATE SENATE DISTRICT: 999 Not Available
STATE HOUSE DISTRICT: 999 Not Available

Point of Contact:

DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE

Cecelia Linder
Program Manager
1315 East West Hwy
SSMC3 F/HC3
Silver Spring, MD 20910
PHONES:  
Office: (301) 713-0174 X162
Fax: (301) 713-0184

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 25-Apr-2024

Chenier Ronquille Barrier Island Restoration DEAUTHORIZED

PROJECT LOCATION:

PROJECT DESCRIPTION:


PROJECT STATUS: (Project Status Last Updated: 25-Sep-2015 )

Project was deauthorized as a CWPPRA project as it was successfully included as a Phase III Early Restoration Project for the Deepwater Horizon Oil Spill.

FUND STATUS:

The current project estimate is $1,042,540 , which includes $1,042,540 for construction first costs, and $0 and $0 for 20 years of monitoring and operations and maintenance, respectively.

LaCoast.gov Project Managers' Technical Factsheet