COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 17-Apr-2024

Delta Building Diversion at Myrtle Grove TRANSFER

PROJECT DATA

PROJECT: Delta Building Diversion at Myrtle Grove TRANSFER
PRIORITY LIST: 10 PROJECT NO: 1002 CWPPRA NO: BA-33 DNR NO: BA-33
PROJECT TYPE: Sediment Diversion NET ACRES BENEFITTED: 8891
REGION: 2 BASIN: Barataria PARISH: Jefferson
LEAD AGENCY: COE
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION:    
DESIGN COMPLETION:    
CONSTRUCTION START:    
CONSTRUCTION COMPLETION:    
ESCROW AMENDMENT No:
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 10-Jan-2001 ( Actual )    
Phase 2 Approval:    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 1 Steve Scalise
STATE SENATE DISTRICT: 1 A. G. Crowe
STATE HOUSE DISTRICT: 105 Christopher J. Leopold

Point of Contact:

DEPT. OF THE ARMY
CORPS OF ENGINEERS

Brad Inman
Project Manager
CEMVN-PM-OR
7400 Leake Avenue
New Orleans, LA 70160
PHONES:  
Office: (504) 862-1940
Fax: (504) 862-1892

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 17-Apr-2024

Delta Building Diversion at Myrtle Grove TRANSFER

PROJECT LOCATION:

The project is in the vicinity of the cities of Myrtle Grove and ironton in Plaquemines Parish, LA.

PROJECT DESCRIPTION:

Project concept involves the diversion of Mississippi River water and sediment for the creation of new emergent wetlands. The alternatives studies under the MRSNFR study involved diversions of 15,000 and 5,000 dfs.

PROJECT STATUS: (Project Status Last Updated: 11-Jul-2002 )

The proposed NMFS/UNO fisheries modeling effort, and its relationship to required EIS input, has been discussed by the principal agencies involved with this project. The current view within the management team is that additional fisheries data collection and analysis will be required over and above the proposed modeling. At this time, it has been decided to begin assembling an inter-agency EIS team and allow them to outline major data and analytic requirements for the NEPA document. The required NEPA scoping meetings have been held and the scoping document is being compliled. An initial Value Engineering study is scheduled for the week of July 22, 2002. WRDA may fund Phase 2.

FUND STATUS:

The current project estimate is $2,543,325 , which includes $2,543,325 for construction first costs, and $0 and $0 for 20 years of monitoring and operations and maintenance, respectively.

LaCoast.gov Project Managers' Technical Factsheet