COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 04-Dec-2024

Bayou Dupont Sediment Delivery-Marsh Creation 3

PROJECT DATA

PROJECT: Bayou Dupont Sediment Delivery-Marsh Creation 3
PRIORITY LIST: 22 PROJECT NO: NA CWPPRA NO: BA-164 DNR NO: BA-164
PROJECT TYPE: Marsh Creation NET ACRES BENEFITTED: 118
REGION: 2 BASIN: Barataria PARISH: Plaquemines
LEAD AGENCY: EPA
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION: 23-Aug-2013 ( Actual )    
DESIGN COMPLETION:    
CONSTRUCTION START: 07-Dec-2015 ( Actual )    
CONSTRUCTION COMPLETION: 29-Jun-2017 ( Actual )    
ESCROW AMENDMENT No:
MONITORING PLAN APPROVAL: 27-Feb-2018 ( Actual )    
O and M PLAN APPROVAL: 11-Sep-2018 ( Actual )    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 24-Jan-2013 ( Actual )    
Phase 2 Approval: 14-May-2015 ( Actual )    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT:
STATE SENATE DISTRICT:
STATE HOUSE DISTRICT:

Point of Contact:

ENVIRONMENTAL PROTECTION AGENCY
REGION 6

Patricia Taylor

EPA Region 6 (6WD-AM)
1201 Elm Street, Suite 500
Dallas, TX 75270
PHONES:  
Office: (214) 665-6403
Fax:

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 04-Dec-2024

Bayou Dupont Sediment Delivery-Marsh Creation 3

PROJECT LOCATION:

PROJECT DESCRIPTION:


PROJECT STATUS: (Project Status Last Updated: 05-Jan-2016 )

Phase 2 was approved at the May 14, 2015 Task Force meeting based on a reduced scope to fit available CWPPRA funding. Phase 2 grant was awarded on December 7, 2015.

FUND STATUS:

The current project estimate is $14,453,415 , which includes $14,081,077 for construction first costs, and $143,308 and $229,031 for 20 years of monitoring and operations and maintenance, respectively.