PROJECT STATUS REPORT as of 04-Dec-2024
PROJECT DATA
PROJECT: Bayou Dupont Sediment Delivery-Marsh Creation 3 |
PRIORITY LIST: 22 | PROJECT NO: NA | CWPPRA NO: BA-164 | DNR NO: BA-164 |
PROJECT TYPE: Marsh Creation | NET ACRES BENEFITTED: 118 |
REGION: 2 | BASIN: Barataria | PARISH: Plaquemines |
LEAD AGENCY: EPA |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
CSA EXECUTION: | 23-Aug-2013 | ( Actual ) | ||
DESIGN COMPLETION: | ||||
CONSTRUCTION START: | 07-Dec-2015 | ( Actual ) | ||
CONSTRUCTION COMPLETION: | 29-Jun-2017 | ( Actual ) | ||
ESCROW AMENDMENT | No: | |||
MONITORING PLAN APPROVAL: | 27-Feb-2018 | ( Actual ) | ||
O and M PLAN APPROVAL: | 11-Sep-2018 | ( Actual ) | ||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 24-Jan-2013 | ( Actual ) | ||
Phase 2 Approval: | 14-May-2015 | ( Actual ) |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | ||
STATE SENATE DISTRICT: | ||
STATE HOUSE DISTRICT: |
Point of Contact:
ENVIRONMENTAL PROTECTION AGENCY
REGION 6
Patricia Taylor EPA Region 6 (6WD-AM) 1201 Elm Street, Suite 500 Dallas, TX 75270 |
|
PROJECT STATUS REPORT as of 04-Dec-2024
Bayou Dupont Sediment Delivery-Marsh Creation 3
PROJECT LOCATION:
PROJECT DESCRIPTION:
PROJECT STATUS: (Project Status Last Updated: 05-Jan-2016 )
Phase 2 was approved at the May 14, 2015 Task Force meeting based on a reduced scope to fit available CWPPRA funding. Phase 2 grant was awarded on December 7, 2015.
FUND STATUS:
The current project estimate is $14,453,415 , which includes $14,081,077 for construction first costs, and $143,308 and $229,031 for 20 years of monitoring and operations and maintenance, respectively.