COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 19-Apr-2024

GIWW to Clovelly Hydrologic Restoration

PROJECT DATA

PROJECT: GIWW to Clovelly Hydrologic Restoration
PRIORITY LIST: 1 PROJECT NO: 0106 CWPPRA NO: BA-2 DNR NO: BA-02
PROJECT TYPE: Hydrologic Restoration NET ACRES BENEFITTED: 175
REGION: 2 BASIN: Barataria PARISH: Lafourche
LEAD AGENCY: NRCS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA.

MILESTONES:

CSA EXECUTION: 17-Apr-1993 ( Actual )    
DESIGN COMPLETION: 30-Aug-1992 ( Actual )    
CONSTRUCTION START: 21-Apr-1997 ( Actual )    
CONSTRUCTION COMPLETION: 31-Oct-2000 ( Actual )    
ESCROW AMENDMENT 18-Nov-1996 ( Actual ) No: 24
MONITORING PLAN APPROVAL: 24-Apr-1997 ( Actual )    
O and M PLAN APPROVAL: 16-Sep-2002 ( Actual )    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 31-Oct-1991 ( Actual )    
Phase 2 Approval: 28-Oct-2009 ( Actual )    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 1 Steve Scalise
STATE SENATE DISTRICT: 20 Norby Chabert
STATE HOUSE DISTRICT: 54 Jerry Gisclair

Point of Contact:

DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE

Quin Kinler



Denham Springs, LA 
PHONES:  
Office:
Fax:

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 19-Apr-2024

GIWW to Clovelly Hydrologic Restoration

PROJECT LOCATION:

PROJECT DESCRIPTION:

The project will protect the 60,000 acres of fresh and low-salinity wetlands through the restoration of historical hydrological conditions. This will promote greater freshwater retention and utilization to prevent rapid salinity increases, and also promote water exchange through sheet flow as opposed to an expanding network of tidal channels. The project will restore the area to the hydrologic conditions that prevailed historically. The project includes canal plugs, rock weirs, fixed crest weirs with boat bays, one variable crest weir, and the rebuilding of low overflow banks that have eroded away.

PROJECT STATUS: (Project Status Last Updated: 06-Dec-2002 )

The project was divided into two contracts in order to expedite implementation. The first contract to install most of the weir structures, began May 1, 1997 and completed November 30, 1997, at a cost of $646,691. The second contract to install bank protection, one weir and one plug, began January 1, 2000 and completed October 31, 2000, at a cost of $3,400,000. All project construction is complete. O&M Plan signed September 16, 2002.

FUND STATUS:

The current project estimate is $12,784,520 , which includes $6,444,428 for construction first costs, and $1,236,624 and $5,103,468 for 20 years of monitoring and operations and maintenance, respectively.

LaCoast.gov Project Managers' Technical Factsheet