PROJECT STATUS REPORT as of 11-Oct-2024
PROJECT DATA
PROJECT: GIWW to Clovelly Hydrologic Restoration |
PRIORITY LIST: 1 | PROJECT NO: 0106 | CWPPRA NO: BA-2 | DNR NO: BA-02 |
PROJECT TYPE: Hydrologic Restoration | NET ACRES BENEFITTED: 175 |
REGION: 2 | BASIN: Barataria | PARISH: Lafourche |
LEAD AGENCY: NRCS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA. |
MILESTONES:
CSA EXECUTION: | 17-Apr-1993 | ( Actual ) | ||
DESIGN COMPLETION: | 30-Aug-1992 | ( Actual ) | ||
CONSTRUCTION START: | 21-Apr-1997 | ( Actual ) | ||
CONSTRUCTION COMPLETION: | 31-Oct-2000 | ( Actual ) | ||
ESCROW AMENDMENT | 18-Nov-1996 | ( Actual ) | No: | 24 |
MONITORING PLAN APPROVAL: | 24-Apr-1997 | ( Actual ) | ||
O and M PLAN APPROVAL: | 16-Sep-2002 | ( Actual ) | ||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 31-Oct-1991 | ( Actual ) | ||
Phase 2 Approval: | 28-Oct-2009 | ( Actual ) |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 1 | Steve Scalise |
STATE SENATE DISTRICT: | 20 | Norby Chabert |
STATE HOUSE DISTRICT: | 54 | Jerry Gisclair |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
Quin Kinler Denham Springs, LA |
|
PROJECT STATUS REPORT as of 11-Oct-2024
GIWW to Clovelly Hydrologic Restoration
PROJECT LOCATION:
PROJECT DESCRIPTION:
The project will protect the 60,000 acres of fresh and low-salinity wetlands through the restoration of historical hydrological conditions. This will promote greater freshwater retention and utilization to prevent rapid salinity increases, and also promote water exchange through sheet flow as opposed to an expanding network of tidal channels. The project will restore the area to the hydrologic conditions that prevailed historically. The project includes canal plugs, rock weirs, fixed crest weirs with boat bays, one variable crest weir, and the rebuilding of low overflow banks that have eroded away.
PROJECT STATUS: (Project Status Last Updated: 06-Dec-2002 )
The project was divided into two contracts in order to expedite implementation. The first contract to install most of the weir structures, began May 1, 1997 and completed November 30, 1997, at a cost of $646,691. The second contract to install bank protection, one weir and one plug, began January 1, 2000 and completed October 31, 2000, at a cost of $3,400,000. All project construction is complete. O&M Plan signed September 16, 2002.
FUND STATUS:
The current project estimate is $13,091,921 , which includes $6,444,428 for construction first costs, and $1,018,824 and $5,628,669 for 20 years of monitoring and operations and maintenance, respectively.