| Project |
Technique |
CWPPRA Partners |
| GIWW (Gulf Intracoastal Waterway) to Clovelly Hydrologic Restoration (BA-02) |
Hydrologic restoration: rock weirs, canal plugs and rock breakwaters reduce saltwater intrusion |
Natural Resources Conservation Service (NRCS) and Louisiana Department of Natural Resources (DNR) |
| Naomi Outfall Management (BA-03c) |
Hydrologic restoration: water control structures manage flow of sediment-laden fresh water from a nearby siphon |
NRCS and DNR |
| Jonathan Davis Wetland Protection (BA-20) |
Hydrologic restoration: water control structures reduce tidal flow and wave action |
NRCS and DNR |
| Barataria Bay Waterway West Side Shoreline Protection (BA-23) |
Shoreline protection: water control structure and rock dike reduce saltwater intrusion and buffer wave energy |
NRCS and DNR |
| Barataria Bay Waterway East Side Shoreline Protection (BA-26) |
Shoreline protection: rock dike stabilizes shoreline, protects marsh from boat wakes and encourages sediment accretion |
NRCS and DNR |
| Barataria Basin Landbridge Shoreline Protection, Phases 1 and 2 (BA-27) |
Shoreline protection: rock dikes and concrete panel structures protect fragile shoreline |
NRCS and DNR |
| Barataria Basin Landbridge Shoreline Protection, Phase 3 (BA-27c) |
Shoreline protection: rock dikes and concrete panel structures protect fragile shoreline |
NRCS and DNR |
| Barataria Basin Landbridge Shoreline Protection Project Phase 4 (BA-27d) |
Shoreline protection: rock dikes protect fragile shoreline |
NRCS and DNR |
| Dedicated Dredging on the Barataria Basin Landbridge (BA-36) |
Marsh creation: dredged sediment delivered via pipeline to build new marsh and nourish existing marsh |
U.S. Fish and Wildlife Service and DNR |
| Little Lake Shoreline Protection/ Dedicated Dredging Near Round Lake (BA-37) |
Shoreline protection and marsh creation: dredged sediment creates new marsh while rock structures shield fragile shoreline |
National Marine Fisheries Service and DNR |
| Mississippi River Sediment Delivery System — Bayou DuPont (BA-39) |
Marsh creation: dredged sediment delivered via pipeline rebuilds wetlands |
Environmental Protection Agency and DNR |
| South Shore of the Pen Shoreline Protection and Marsh Creation (BA-41) |
Shoreline protection and marsh creation: concrete and rock structures protect shoreline; dredged sediment builds new marsh |
NRCS and DNR |