From water to wetlands
Pipeline Projects Build New Marsh

IN THE UNITED STATES PIPELINE SEDIMENT TRANSFER is a relatively new tool for wetland restoration, but in coastal Louisiana it’s already been successful.

Since 1994, Breaux Act projects using piped sediment have created more than 3,000 acres of new land. Some experts say we’ve only scratched the surface of the technique’s potential.

“Conceivably, we could use this technology to offset all of our land loss,” says coastal oceanographer Dr. Joe Suhayda. “We could stop the loss of Louisiana’s coast.”

The success of three pipeline transport projects — at Bayou LaBranche, at West Bay, and on Timbalier Island— illustrates the technique’s land-building potential.

Lake Pontchartrain
LaBranche Wetlands
I-10
BEFORE
BEFORE
Billy Hicks, USACE
Lake Pontchartrain
LaBranche Wetlands
I-10
AFTER
Billy Hicks, USACE

A Successful Start

As Interstate 10 travelers sweep past the southern shore of Lake Pontchartrain, they look out over one of the Breaux Act’s first success stories: the lush, green wetlands near Bayou LaBranche.

Just a decade ago, the area was open water — the result of more than 150 years of subsidence, flooding and erosion that began when railroad construction in the 1830s altered the flow of water through the wetland. By the 1990s, only a narrow strip of marsh separated the ponds from Lake Pontchartrain.

The Bayou LaBranche Wetland Creation project, located just east of the Bonnet Carre Spillway near New Orleans, involved dredging sediment from the bottom of Lake Pontchartrain, then pumping it through a 7,500-footlong pipeline to the open water area. In four weeks, nearly 2.7 million cubic yards of sediment were placed to create 300 acres of land.

“With the Bayou LaBranche project, it was immediately obvious we would be able to use this technique to create marsh,” says Gregory Miller, project manager with the U.S. Army Corps of Engineers. “Because LaBranche is one of the most visible Breaux Act projects, people who remember the area as open water can view these wetlands, and see that it’s possible to literally build land.”

West Bay diversion channel
As the pipeline dredge California dug the West Bay Diversion channel through the right bank of the Mississippi River, the sand mined from the bank was pumped through a pipeline to the deteriorating marsh of West Bay (at left in photo). The project created new wetlands, which the river will sustain and enlarge when high stage flows naturally divert into the marsh.
Greg Miller, USACE

Pipeline, Diversion Restore Marsh

West Bay embodies one of the ironies of wetland loss: though only a few yards from the sediment-rich waters of the Mississippi, the marsh subsided and converted to open water.

To restore the marsh, the West Bay Sediment Diversion project, located about five miles from the river’s Head of Passes, required dredging a 440-foot-wide, 25-foot-deep channel from the river to the bay, and pumping the dredged material into the bay’s open water area.

“The goal of the project was to create a diversion through which sediment-laden water would flow naturally to the marsh during high river stages, creating land over the course of 20 years,” Miller explains. “But by pumping in the dredged material from the channel, we were able to restore 200 acres right away.”

Marsh creation in West Bay will continue, Miller says, as sediment dredged from the river to maintain the navigation channel is used to build more wetlands. Over the long term, however, the diversion itself will nourish and continue building marsh.“This project shows how well piped sediment complements other restoration methods. It jump-started the land-building process, and the river will do the rest.”

Fortifying Barrier Islands

Louisiana’s barrier islands, the coast’s first line of defense against hurricanes, are eroding even more rapidly than the inland marshes they protect.

“In the past, the Mississippi River directed sediment toward barrier islands, but today the river sends sediment off into the gulf,” explains Beverly Ethridge, environmental scientist with the Environmental Protection Agency. “As storms wash away sand from these islands, there is nothing to replace it.”

Timbalier Island, a narrow strip of land south of Terrebonne Bay, had suffered extensive hurricane damage. “We knew this barrier island would vanish within 50 years if it didn’t receive new sediment,” says Patty Taylor, EPA project manager.

Timbalier Island Dune and Marsh Restoration project
In the Timbalier Island Dune and Marsh Restoration project, a pipeline dredge was used to collect sand from the floor of the Gulf of Mexico. “That’s one of the unique features of this project,” says the EPA’s Beverly Ethridge. “By pumping sand from three miles offshore, this project brought new sediment into a sedimentstarved environment.”
Chris Williams, LADNR

In the Timbalier Island Dune and Marsh Restoration project, 4.6 million cubic yards of sand were pumped to the island from three miles out in the gulf. The project was the first to use sand from so far offshore, says Taylor, who explains that sand dredged from the gulf is superior to that harvested closer to land.

“The high quality sand performed even better than expected,” says Chris Williams, project manager for the Louisiana Department of Natural Resources. “We were able to complete the project $3.5 million under budget while creating more land than was originally intended, for a total gain of approximately 400 acres.”

The Timbalier Island project is another example of the potential of pipeline transport, Suhayda says.

“Pipeline transport is unique among restoration techniques in that it can truly restore land, rather than merely slow the rate of loss,” Suhayda says. “Within weeks, open water can become land.

Pipe Dreams: the Future of Pipeline Transport

Pipeline transport is still evolving as a restoration technique, but its use is increasing. Since the Bayou LaBranche restoration in 1994, over a dozen Breaux Act projects have included piped sediment, and several more are planned. In the Scofield Bayou area, the Riverine Sand Mining/ Scofield Island Restoration project (Plaquemines Parish) calls for pumping Mississippi River sediment 10 miles to restore the eroded and subsiding shoreline. The Mississippi River Sediment Delivery System— Bayou Dupont project (Plaquemines and Jefferson parishes) will restore broken marsh using sediment pumped from the river. The Pass Chaland to Grand Bayou Pass Shoreline Restoration project (Plaquemines Parish) will use dredged sediment to restore beach, dune and marsh to bolster the fragile shore of Bay Joe Wise. And two planned projects will mine sediment from Ship Shoal to rebuild barrier islands in the severely eroded Isles Dernieres chain: the Ship Shoal: Whiskey West Flank Restoration project, which will transport sediment approximately eight miles to rebuild dune and marsh habitat on Whiskey Island; and the New Cut Dune and Marsh Restoration project, which calls for pumping sand 10 to 12 miles to close New Cut, a breach between East and Trinity islands.