The Coastal Crisis and Louisiana's Response

Even a cursory review of the data shows that Region Four, like all of coastal Louisiana, has suffered severe wetland loss in the last century. From 1932 to 1990, the region lost approximately 25 percent of its wetlands. The causes of this dramatic loss are commonly cited as:

"While significant dollars have been committed to Region Four, significant is not enough."
Paul Coreil, Assistant Director, Environmental Affairs at LSU

Looking into the future, scientists project that the region will lose an additional 13 percent of its wetlands by the year 2050. While this is the lowest loss projection among the four Coast 2050 regions, it represents the disappearance of 100,000 additional acres of marsh.

US Army Corps of Engineers Photo
US Army Corps of Engineers Photo

Although many people living in the Vermilion, Cameron and Calcasieu parishes had been aware of the problem for decades, its full dimension was not quantified until mapping studies were completed in the 1970s. These studies gave citizens and political leaders the scientific data they needed to push through a series of federal initiatives that culminated in the Breaux Act of 1990. Coast 2050, approved in 1998, provided the all-important comprehensive strategic plan that an effective response required.

Coast 2050 identifies three broad habitat objectives for Region Four:

  1. maintain most of the habitat in the northeast portion of the region (Lakes Subbasin) as fresh and intermediate marsh
  2. convert the existing saline and brackish marshes in the southeast portion of the region (Chenier Subbasin) to brackish and intermediate marshes
  3. create fresher conditions in the Calcasieu-Sabine Basin by converting the central portion to fresh marsh and the remainder to intermediate marsh

The Breaux Act projects listed in the following chart summarize the concrete action that has been taken thus far to preserve and restore the marsh in Region Four.

Region Four CWPPRA Projects: Construction Status

Project Name Description of
Project Work
Acres Benefited Completion Date Construction
Status
Cameron-Creole Plugs installation of two plugs with small boat bays in the Calcasieu Lake Levee Borrow Canal to prevent saltwater intrusion 865 28-Jan-97 construction complete, monitoring in progress
Sabine National Wildlife Refuge Erosion Protection construction of a rock dike along Burton Sutton Canal and revetment along Starks Canal, rock armoring of three water control structures and installation of three alligator crossings 5,542 1-Mar-95 construction complete, monitoring in progress
Brown Lake's Hydrologic Restoration construction of earthen terraces and boundary levee, vegetative plantings, installation of two water control structures and one freshwater introduction structure 282 1-Feb-02 modeling underway
Mud Lake Hydrologic Restoration boundary levee rehabilitation, 15,000 linear feet of vegetative plantings, installation of 16 water control structures 1,520 15-Jun-96 construction complete, monitoring in progress
Highway 384 Hydrologic Restoration installation of culverts and channel rip-rapping, construction of shoreline breach plugs, vegetative plantings and maintenance of the perimeter levee 150 7-Jan-00 construction complete,
Clear Marais Shore Protection construction of six miles of rock-armored breakwater 1,067 3-Mar-97 construction complete, monitoring in progress
Cameron-Creole Maintenance repair of the Grand Bayou structure, rock placement and ongoing maintenance 2,602 15-Jul-98 first three maintenance contracts complete
Replace Hog Island, West Cove and Headquarters Canal structures replacement of existing structures to increase discharge potential and management flexibility 953 Spring-01 under construction
Perry Ridge Shoreline Protection installation of 12,000 linear feet of rock dike to reduce erosion and decrease the potential of saltwater intrusion 1,203 15-Feb-99 construction complete, monitoring in progress
Sweet Lake/Willow Lake Hydrologic Restoration plantings of California Bulrush, installation of rip-rap rock embanks and construction of terraces 247 1-Mar-00 bank protection complete, plantings and terraces to be built in spring 2001
Black Bayou Hydrologic Restoration installation of a rock dike, installation of two weirs, replacement of culverts, installation of a ditch plug and a canal plug, installation of rock liner and 133,000 linear feet of vegetative plantings 3,594 1-Jun-02  engineering and design underway
Cameron Prairie National Wildlife Refuge Shoreline Protection construction of 6,000 linear feet of rock breakwater 247 9-Aug-94 construction complete, monitoring in progress
Freshwater Bayou Wetlands bank protection and installation of eight variable-crest weirs 1,593 pending bank protection complete, weirs scheduled in future
Freshwater Bayou Canal Bank Stabilization construction of 23,350 linear feet of rock dike 511 15-Jun-98 construction complete
Pecan Island Terracing extensive construction of earthen terraces 442 1-Feb-02 engineering design underway, land rights being negotiated