Status Report: Breaux Act Projects Approved and Completed

A map of the CWPPRA basins

Mermentau Basin

Project  Agency  Const. Comp.
Humble Canal NRCS
Pecan Island Terracing NMFS
Cameron Prairie Refuge Shoreline Protection FWS 09-Aug-94
Freshwater Bayou Bank Stabilization NRCS 15-Jun-98
Freshwater Bayou NRCS 15-Aug-98


Calcasieu/Sabine Basin

Project  Agency  Const. Comp.
Sabine Refuge Marsh Creation, Phase One COE
Black Bayou Hydrologic Restoration NMFS
Brown Lake NRCS
Compost Demo EPA
Hwy 384 NRCS
Perry Ridge Bank Protection NRCS 15-Feb-99
Plowed Terraces Demo NRCS
Sabine Refuge Structures (Hog Island) FWS
Sweet Lake/Willow Lake NRCS
Vegetative Plantings Demo - West Hackberry NRCS 30-Mar-94
Sabine Wildlife Refuge Erosion Protection FWS 01-Mar-95
Mud Lake NRCS 15-Jun-96
Cameron Creole Watershed Hydrologic Restoration FWS 28-Jan-97
Clear Marais Bank Protection COE 03-Mar-97
Cameron Creole Maintenance NRCS 15-Jul-98


Atchafalaya Basin

Project Agency Const. Comp.
Big Island Mining (Increment 1) NMFS 8-Oct-98
Atchafalaya Sediment Delivery NMFS 21-Mar-98


Teche Vermilion Basin

Project  Agency Const. Comp.
Lake Portage NRCS
Cheniere au Tigre Sediment Trapping Device Demo NRCS
Cote Blanche NRCS 15-Dec-98
Jaws Sediment Trapping NMFS
Little Vermilion Bay Sediment Trapping NMFS
Marsh Island Hydrologic Restoration COE
Oaks/Avery Canals Hydrologic Restoration-Incr 1 (B.S. only) NRCS
Vermilion Bay/Boston Canal NRCS 30-Nov-95
Vermilion River Cutoff Bank Protection COE 11-Feb-96


Terrebonne Basin

Project Agency Const. Comp.
Bayou Lafourche Siphon EPA
Brady Canal NRCS
East Timbalier Island Sediment Restoration #1 NMFS
East Timbalier Island Sediment Restoration #2 NMFS
Flotant Marsh Fencing Demo NRCS
Grand Bayou/GIWW Freshwater Introduction FWS
Isles Dernieres (Phase 0) (East Island) EPA 24-Oct-98
Isles Dernieres (Phase 1) (Trinity Island) EPA 22-Oct-98
Lake Boudreaux FW Introduction, Alt B FWS
Lake Chapeau Sediment & Hydrologic Restoration NMFS
Penchant Basin Plan w/o Shoreline Stabilization NRCS
Vegetative Plantings Demo-Timbalier Island NRCS 30-Jul-96
Vegetative Plantings Demo-Falgout Canal NMFS 30-Dec-96
Point Au Fer NMFS  08-May-97
Raccoon Island Breakwaters Demo NRCS  31-Jul-97
West Belle Pass Headland Restoration COE 17-Jul-98
Whiskey Island Restoration (Phase 2) EPA 25-Aug-98
Thin Mat Floating Marsh NRCS


Pontchartrain Basin

Project Agency Const. Comp.
Bayou Bienvenue NMFS
Hopedale NMFS
Bayou Chevee Shoreline Protection COE
Fritchie Marsh NRCS
MRGO Back Dike Marsh Protection COE 29-Jan-99
Red Mud Demo EPA
Violet Freshwater Distribution NRCS
Bayou LaBranche Wetlands Restoration COE 07-Apr-94
Bayou Sauvage #1 FWS 30-May-96
Bayou Sauvage #2 FWS 28-May-97


Barataria Basin

Project Agency Const. Comp.
Barataria Basin Landbridge, Ph 2 NRCS
BA-2 GIWW to Clovelly Wetland Restoration NRCS
Barataria Basin Landbridge, Ph 1 NRCS
Barataria Bay Marsh Creation COE
Bayou L'Ours Ridge Hydrologic Restoration NRCS
BBWW "Dupre Cut" - East NRCS
BBWW "Dupre Cut" - West NRCS
Grand Terre Vegetative Plantings  NMFS
Jonathan Davis Wetland NRCS
Myrtle Grove Siphon  NMFS
Naomi Outfall Management NRCS
West Pointe-a-la-Hache Outfall Management NRCS
Lake Salvador Shoreline Protection COE 21-Mar-96
Lake Salvador Shore Protection Demo NMFS 30-Jun-98


Mississippi River Delta Basin

Project Agency Const. Comp.
Delta-Wide Crevasses NMFS
Dustpan/Cutterhead Dredge Demo COE
Hopper Dredge Demo COE
West Bay Sediment Diversion COE
Channel Armor Gap Crevasse COE 02-Nov-97


Breton Sound Basin

Project  Agency Const. Comp.
Caernarvon Outfall Management NRCS
Upper Oaks River NRCS


Note:
All coastal basins include the Nutria Harvest for Wetland Restoration Demonstration Project, sponsored by the U.S. Fish and Wildlife Service.