PROJECT STATUS REPORT as of 20-Nov-2009
PROJECT DATA
| PROJECT: Ship Shoal: Whiskey West Flank Restoration |
| PRIORITY LIST: 11 | PROJECT NO: 1105 | CWPPRA NO: TE-14-1 | DNR NO: TE-47 |
| PROJECT TYPE: Barrier Island | NET ACRES BENEFITTED: 195 |
| REGION: 3 | BASIN: Terrebonne | PARISH: Terrebonne |
| LEAD AGENCY: EPA |
| LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
| CSA EXECUTION: | 17-Mar-2004 | ( Actual ) | ||
| DESIGN COMPLETION: | 17-Jan-2005 | * | ||
| CONSTRUCTION START: | 1-May-2010 | |||
| CONSTRUCTION COMPLETION: | 1-Feb-2011 | |||
| ESCROW AMENDMENT | No: | |||
| MONITORING PLAN APPROVAL: | ||||
| O and M PLAN APPROVAL: | ||||
| DEAUTHORIZATION DATE: | ||||
| CASH FLOW PROECTS: | ||||
| Phase 1 Approval: | 1/16/2002 | ( Actual ) | ||
| Phase 2 Approval: | 20-Jan-2010 |
LEGISLATIVE DISTRICTS:
| CONGRESSIONAL DISTRICT: | 3 | Charlie Melancon |
| STATE SENATE DISTRICT: | 20 | |
| STATE HOUSE DISTRICT: | 999 | Not Available |
Point of Contact:
ENVIRONMENTAL PROTECTION AGENCY
REGION 6
| Brad Crawford (6WQ-EMC) Project Manager EPA Region 6 1445 Ross Ave. Dallas, TX 75202-2733 |
|
PROJECT STATUS REPORT as of 20-Nov-2009
Ship Shoal: Whiskey West Flank Restoration
PROJECT LOCATION:
Western end of Whiskey Island of the Isles Dernieres Chain of Barrier Islands, Terrebonne Parish, LA
PROJECT DESCRIPTION:
Mine and transport sand approximately 8 miles from the "Ship Shoal" offshore sand body to rebuild dunes and marsh platform.
PROJECT STATUS: (Project Status Last Updated: 5-Dec-2008 )
The project's cost data was updated and a revised Phase 2 request was presented to the Technical Committee on December 3, 2008.
FUND STATUS:
The current project estimate is $3,742,053 , which includes $3,717,855 for construction first costs, and $24,198 and $0 for 20 years of monitoring and operations and maintenance, respectively.