PROJECT STATUS REPORT as of 9-Feb-2010
PROJECT DATA
| PROJECT: New Cut Dune and Marsh Restoration |
| PRIORITY LIST: 9 | PROJECT NO: 0906 | CWPPRA NO: TE-11a | DNR NO: TE-37 |
| PROJECT TYPE: Barrier Island | NET ACRES BENEFITTED: 102 |
| REGION: 3 | BASIN: Terrebonne | PARISH: Terrebonne |
| LEAD AGENCY: EPA |
| LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
| CSA EXECUTION: | 1-Sep-2000 | ( Actual ) | ||
| DESIGN COMPLETION: | 1-Feb-2001 | ( Actual ) | ||
| CONSTRUCTION START: | 1-Oct-2006 | ( Actual ) | ||
| CONSTRUCTION COMPLETION: | 30-Sep-2008 | ( Actual ) | ||
| ESCROW AMENDMENT | 2-Mar-2001 | ( Actual ) | No: | 83 |
| MONITORING PLAN APPROVAL: | ||||
| O and M PLAN APPROVAL: | ||||
| DEAUTHORIZATION DATE: | ||||
| CASH FLOW PROECTS: | ||||
| Phase 1 Approval: | 1/11/2000 | ( Actual ) | ||
| Phase 2 Approval: | 10-Jan-2001 | ( Actual ) |
LEGISLATIVE DISTRICTS:
| CONGRESSIONAL DISTRICT: | 3 | Charlie Melancon |
| STATE SENATE DISTRICT: | 20 | |
| STATE HOUSE DISTRICT: | 53 | Damon J. Baldone |
Point of Contact:
ENVIRONMENTAL PROTECTION AGENCY
REGION 6
| Paul Kaspar , |
|
PROJECT STATUS REPORT as of 9-Feb-2010
New Cut Dune and Marsh Restoration
PROJECT LOCATION:
Isles Dernieres Barrier Island Chain, Terrebonne Parish, LA.
PROJECT DESCRIPTION:
Barrier island dunes and marsh will be created in the cut established during Hurricane Juan. Sediment source is located offshore.
PROJECT STATUS: (Project Status Last Updated: 27-Aug-2009 )
Lessoned learned meeting was held on April 23, 2008. LDNR grant for Phase II construction activities was closed-out on September 30, 2008. Remaining Phase II increment activities included on-going annual inspections.
FUND STATUS:
The current project estimate is $13,110,435 , which includes $12,678,829 for construction first costs, and $120,218 and $311,388 for 20 years of monitoring and operations and maintenance, respectively.