COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 31-Jul-2010

River Reintroduction into Maurepas Swamp

PROJECT DATA

PROJECT: River Reintroduction into Maurepas Swamp
PRIORITY LIST: 11 PROJECT NO: 1101 CWPPRA NO: XPO-500 DNR NO: PO-29
PROJECT TYPE: Freshwater Diversion NET ACRES BENEFITTED: 5438
REGION: 1 BASIN: Pontchartrain PARISH: St. John the Baptist
LEAD AGENCY: EPA
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION: 4-Apr-2002 ( Actual )    
DESIGN COMPLETION: 1-Mar-2012    
CONSTRUCTION START: 1-Nov-2013    
CONSTRUCTION COMPLETION: 1-Nov-2016    
ESCROW AMENDMENT No:
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 8/7/2001 ( Actual )    
Phase 2 Approval: 16-Jan-2013    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 3 Charlie Melancon
STATE SENATE DISTRICT: 999 Not Available
STATE HOUSE DISTRICT: 999 Not Available

Point of Contact:

ENVIRONMENTAL PROTECTION AGENCY
REGION 6

Ken Teague (6WQ-EMC)
Project Manager
EPA Region 6
1445 Ross Ave.
Dallas, TX 75202-2733
PHONES:  
Office: (214) 665-6687
Fax: (214) 665-6689

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 31-Jul-2010

River Reintroduction into Maurepas Swamp

PROJECT LOCATION:

Swamps south of Lake Maurepas, St. John the Baptist, St. James, and Ascension Parishes, Louisiana.

PROJECT DESCRIPTION:

The project will divert 1,500 cfs river water, through a diversion structure in the Mississippi River levee, into a 5-mile outflow channel, and into Maurepas Swamps. Maurepas Diversion has a total project area of 36,121 acres. The 36,121 acre area is benefitted by tree growth being improved and overall forest health will improve. The area would be substantially degraded without the project.

PROJECT STATUS: (Project Status Last Updated: 12-Mar-2009 )

30% Design Review meeting was held on December 4, 2008. Comments were received. Responses to comments are being drafted. The post-30% Design Review letter to the CWPPRA Technical Committee, as required by the CWPPRA SOP, is under development. 95% design will be complete in the late summer of 2010.

FUND STATUS:

The current project estimate is $6,780,307 , which includes $6,731,444 for construction first costs, and $48,863 and $0 for 20 years of monitoring and operations and maintenance, respectively.