PROJECT STATUS REPORT as of 31-Oct-2024
PROJECT DATA
PROJECT: Fritchie Marsh Restoration |
PRIORITY LIST: 2 | PROJECT NO: 0221 | CWPPRA NO: PO-6 | DNR NO: PO-06 |
PROJECT TYPE: Hydrologic Restoration | NET ACRES BENEFITTED: 1040 |
REGION: 1 | BASIN: Pontchartrain | PARISH: St. Tammany |
LEAD AGENCY: NRCS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA. |
MILESTONES:
CSA EXECUTION: | 21-Feb-1995 | ( Actual ) | ||
DESIGN COMPLETION: | 30-Jun-1999 | ( Actual ) | ||
CONSTRUCTION START: | 01-Nov-2000 | ( Actual ) | ||
CONSTRUCTION COMPLETION: | 01-Mar-2001 | ( Actual ) | ||
ESCROW AMENDMENT | 24-Aug-1995 | ( Actual ) | No: | 35 |
MONITORING PLAN APPROVAL: | ||||
O and M PLAN APPROVAL: | 29-Jan-2003 | ( Actual ) | ||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 19-Oct-1992 | ( Actual ) | ||
Phase 2 Approval: | 19-Oct-1992 | ( Actual ) |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 1 | Steve Scalise |
STATE SENATE DISTRICT: | 11 | Jack Donahue |
STATE HOUSE DISTRICT: | 90 | Gregory Cromer |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
Quin Kinler Denham Springs, LA |
|
PROJECT STATUS REPORT as of 31-Oct-2024
Fritchie Marsh Restoration
PROJECT LOCATION:
PROJECT DESCRIPTION:
The purpose of the project is to achieve remediation of the causes of wetland loss in the area and to improve habitat for wildlife and fisheries. This will be accomplished by increasing the flow of fresh water into the marsh and managing the outfall. Project features include diverting part of the W-14 canal, and installing larger culverts under Hwy 90.
PROJECT STATUS: (Project Status Last Updated: 12-Mar-2003 )
O&M plan executed January 29, 2003.
FUND STATUS:
The current project estimate is $2,201,674 , which includes $1,060,816 for construction first costs, and $815,647 and $325,211 for 20 years of monitoring and operations and maintenance, respectively.
LaCoast.gov | Project Managers' Technical Factsheet |