PROJECT STATUS REPORT as of 31-Oct-2024
PROJECT DATA
PROJECT: South White Lake Shoreline Protection |
PRIORITY LIST: 12 | PROJECT NO: 1205 | CWPPRA NO: ME-22 | DNR NO: ME-22 |
PROJECT TYPE: Shoreline Protection | NET ACRES BENEFITTED: 844 |
REGION: 4 | BASIN: Mermentau | PARISH: Vermilion |
LEAD AGENCY: COE |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
CSA EXECUTION: | 24-Mar-2005 | ( Actual ) | ||
DESIGN COMPLETION: | 03-Sep-2004 | ( Actual ) | ||
CONSTRUCTION START: | 01-Nov-2005 | ( Actual ) | ||
CONSTRUCTION COMPLETION: | 29-Aug-2006 | ( Actual ) | ||
ESCROW AMENDMENT | 11-May-2005 | ( Actual ) | No: | 109 |
MONITORING PLAN APPROVAL: | ||||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 16-Jan-2003 | ( Actual ) | ||
Phase 2 Approval: | 13-Oct-2004 | ( Actual ) |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 3 | Charles W. Boustany |
STATE SENATE DISTRICT: | 25 | Dan "Blade" Morrish |
STATE HOUSE DISTRICT: | 47 | Bob Hensgens |
Point of Contact:
DEPT. OF THE ARMY
CORPS OF ENGINEERS
Susan Hennington Biologist CEMVN-PM-OR 7400 Leake Avenue New Orleans, LA 70160-0267 |
|
PROJECT STATUS REPORT as of 31-Oct-2024
South White Lake Shoreline Protection
PROJECT LOCATION:
PROJECT DESCRIPTION:
11 Mar 2008 Construction completed in August 2006; monitoring efforts on-going.
PROJECT STATUS: (Project Status Last Updated: 20-Jun-2014 )
CPRA O&M is in the process of setting up the 2014 annual site inspection trip for the ME-22 project; it is tentatively set to occur in the late June or early July 2014 timeframe with report to follow.
FUND STATUS:
The current project estimate is $10,918,620 , which includes $10,449,281 for construction first costs, and $130,685 and $338,655 for 20 years of monitoring and operations and maintenance, respectively.
LaCoast.gov | Project Managers' Technical Factsheet |