PROJECT STATUS REPORT as of 31-Oct-2024
PROJECT DATA
PROJECT: Cameron-Creole Maintenance |
PRIORITY LIST: 3 | PROJECT NO: 0333 | CWPPRA NO: CS-4a | DNR NO: CS-04a |
PROJECT TYPE: Hydrologic Restoration | NET ACRES BENEFITTED: 2602 |
REGION: 4 | BASIN: Calcasieu/Sabine | PARISH: Cameron |
LEAD AGENCY: NRCS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA. |
MILESTONES:
CSA EXECUTION: | 09-Jan-1997 | ( Actual ) | ||
DESIGN COMPLETION: | 15-Jan-1997 | ( Actual ) | ||
CONSTRUCTION START: | 30-Sep-1997 | ( Actual ) | ||
CONSTRUCTION COMPLETION: | 30-Sep-1997 | ( Actual ) | ||
ESCROW AMENDMENT | 12-May-1997 | ( Actual ) | No: | 45 |
MONITORING PLAN APPROVAL: | ||||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 01-Oct-1993 | ( Actual ) | ||
Phase 2 Approval: |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 3 | Charles W. Boustany |
STATE SENATE DISTRICT: | 25 | Dan "Blade" Morrish |
STATE HOUSE DISTRICT: | 36 | Chuck Kleckley |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
Quin Kinler Denham Springs, LA |
|
PROJECT STATUS REPORT as of 31-Oct-2024
Cameron-Creole Maintenance
PROJECT LOCATION:
PROJECT DESCRIPTION:
The project area falls within the Cameron-Creole watershed management area, which has been adversely impacted by saltwater intrusion and loss of sediments due to channelization and water diversion of the Calcasieu River. The project will provide maintenance for the existing 19 miles of levee and five major structures which make up the Cameron-Creole Watershed Project.
PROJECT STATUS: (Project Status Last Updated: 01-Jan-1990 )
The first three contracts for maintenance work are complete. The project provides for maintenance on an as-needed basis.
FUND STATUS:
The current project estimate is $9,398,147 , which includes $0 for construction first costs, and $895,036 and $8,503,111 for 20 years of monitoring and operations and maintenance, respectively.