COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 31-Oct-2024

Bayou Lours Ridge Hydrologic Restoration DEAUTHORIZED

PROJECT DATA

PROJECT: Bayou Lours Ridge Hydrologic Restoration DEAUTHORIZED
PRIORITY LIST: 4 PROJECT NO: 0449 CWPPRA NO: PBA-34 DNR NO: BA-22
PROJECT TYPE: Hydrologic Restoration NET ACRES BENEFITTED:
REGION: 2 BASIN: Barataria PARISH: Lafourche
LEAD AGENCY: NRCS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION: 23-Jun-1997 ( Actual )    
DESIGN COMPLETION:    
CONSTRUCTION START:    
CONSTRUCTION COMPLETION:    
ESCROW AMENDMENT 25-Aug-1997 ( Actual ) No: 50
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE: 16-Apr-2003      
CASH FLOW PROECTS:        
Phase 1 Approval: 16-Dec-1994 ( Actual )    
Phase 2 Approval:    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 1 Steve Scalise
STATE SENATE DISTRICT: 20 Norby Chabert
STATE HOUSE DISTRICT: 54 Jerry Gisclair

Point of Contact:

DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE

Quin Kinler



Denham Springs, LA 
PHONES:  
Office:
Fax:

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 31-Oct-2024

Bayou Lours Ridge Hydrologic Restoration DEAUTHORIZED

PROJECT LOCATION:

PROJECT DESCRIPTION:

Bayou L'Ours was historically a distributary of Bayou LaFourche. The natural levees of this bayou created the L'Ours subbasin, which has been breached by access and pipeline canals. The breaches have increased tidal exchange, reduced freshwater retention, and increased salinities in the marshes within the upper subbasin. Plugs will be placed on six canals, and water control structures containing boat bays to accommodate small boat traffic will be installed on two others to restore the hydrologic integrity of the ridge.

PROJECT STATUS: (Project Status Last Updated: 12-Mar-2003 )

The initial step of deauthorization was taken at the January Task Force meeting. The process will be finalized at the April Task Force meeting.

FUND STATUS:

The current project estimate is $371,232 , which includes $265,334 for construction first costs, and $105,899 and $0 for 20 years of monitoring and operations and maintenance, respectively.

LaCoast.gov Project Managers' Technical Factsheet